Skip to content

02 / Pressure pipe rehabilitation

IBB16 Pressure Pipe Lining

Pressure pipe rehabilitation starts with the operating conditions, the existing pipe and its connections. IBB16 combines liners with different properties and curing systems to provide a rehabilitation option for suitable pipelines. Application, design and acceptance requirements are established during project assessment.

Illustrative cross-section showing liner material within an existing pressure pipe
MULTIPIPE / TECHNICAL SERVICES02 / 07
01 / Project assessment

Applications

Rehabilitation feasibility studies for suitable pressure pipelines

Repair and shutdown planning for networks such as cooling water mains

Lining projects requiring coordinated end connections, valves and branches

Selection considerations

Assessment considers the conveyed fluid, pressure and temperature conditions, host material, bends, ends and branch connections. IBB16 does not rely on bonding to the old pipe as its system principle. A close fit is different from structural bonding. Potable-water or other special applications require their own material and suitability checks.

02 / From survey to verification

Delivery approach

  1. Assess operating conditions

    Review drawings, service requirements and known defects to define the pipe section and the conditions the proposed system must address.

  2. Plan the interfaces

    Coordinate isolation, draining, cleaning and shutdown windows while reviewing installation access and the end-connection arrangements.

  3. Define the installation

    Develop lining, curing and connection work around the selected system and the engineering design for the actual pipe.

  4. Test and return to service

    Agree the required inspections and tests, together with the responsibilities and arrangements for handover and recommissioning.

03 / Project coordination

Planning & records

Records to agree during planning

  • Operating-condition and proposal information within the assessment scope
  • Material documents confirmed for the selected system and application
  • Installation and inspection records specified by the contract
  • Agreed test results and handover information

Useful information for an enquiry

  • Conveyed fluid, operating pressure and temperature information
  • Route drawings, internal diameter, material and bends
  • Valve, branch and end-connection details
  • Shutdown requirements, existing surveys and acceptance specifications

The scope, testing methods, record formats and acceptance criteria are agreed against site findings, client or consultant requirements and the contract.

Download the enquiry checklist (.txt)
04 / Before you begin

Common questions

Do the published maximum specifications apply to every project?

No. Product data supports selection, but actual suitability depends on operating conditions, pipe condition, material configuration and connection design. These must be checked for the individual project.

Can the system be used directly in a drinking-water main?

The specified material system, application requirements and supporting documents must first be checked. A manufacturer's general drinking-water description does not replace project-specific assessment.

Related services

Technical referencesMultiPipe — Services ↗IBG HydroTech — IBB16 ↗

Start with the conditions on site.

Share the location, pipe dimensions, operating use and available inspection records to discuss the next step with our engineering team.